 |
RAITO, INC. - Geotechnical
Construction Specialists
     |
|
|
|
|
 |
|
| |
| Port of Oakland Berths 55/56 - Oakland, California,
USA |
The construction of Berths 55/56 at the Port of Oakland required the
stabilization of a cut slope under a proposed container wharf, extending 2,400
feet long and 124 feet wide. The cut slope was constructed to transition soil
backlands to the design dredge depth for a maximum slope height of 65 feet.
Soil conditions encountered on the project consisted of surface
fill, Bay Mud and Young Bay Deposits described as soft, weak and/or susceptible
to seismically induced liquefaction and lateral spreading. This condition posed
a potential threat to the stability of the proposed wharf structures during and
after major earthquakes. A CDSM buttress system was proposed to provide
shoreline stabilization and control lateral spreading.
The soil-cement buttress consisting of a rectangular grid of
Cement Deep Soil Mixed (CDSM) walls was formed using 3-foot diameter columns
spaced on 2-foot centers. The grid consisted of two longitudinal walls parallel
to the shoreline spaced 32 feet apart, and a series of transverse walls
perpendicular to the shoreline spaced nine feet apart. The transverse walls
served as the primary source of soil stability while the longitudinal walls
provide end restraint for the transverse walls and contain the potentially
liquefiable fill behind the buttress.
A CDSM test section was performed prior to full production to
verify that the CDSM equipment, procedures and mix design could produce the
required soil improvement as well as to assess the impact of wharf pile driving
on the CDSM walls. Results from the test section demonstrated that the CDSM
walls would provide adequate stabilization of the shoreline, satisfying the
geometric, strength design and uniformity requirements. The test section also
demonstrated that the driving of wharf piles would not adversely affect the CDSM
buttress. The use of the CDSM method allowed for the owner to capitalize on
noteworthy cost and schedule benefits.
Over 36,000 cubic yards of CDSM ground stabilization was
constructed over a period of five months. Triple-shaft CDSM equipment was used
for ground stabilization to a maximum depth of 38 feet. Drilling depth,
penetration/withdrawal speed, shaft rotation and slurry injection rates were
monitored in real-time and recorded in 3-foot depth increments to assure
accurate control and a uniformly mixed soil-cement product.
Test specimens for unconfined compressive strength were retrieved
by a triple barrel coring system, and exceeded the acceptance criteria of an
average 160 psi at 28 days.
|

Triple auger rig.

Oakland Ports.

CDSM test section.

A typical CDSM element. |
| |
| Port of Oakland - Berths 57/58 - Oakland California,
USA |
The construction of Berths 57/58 at the Port of Oakland required the
stabilization of a cut slope under a proposed container wharf extending 2,400
feet. The cut slope was constructed to transition soil backlands to the design
dredge depth for a maximum slope height of 65 feet.
Soil conditions encountered on the project consisted of surface
fill, Bay Mud and Young Bay Deposits described as soft, weak and/or susceptible
to seismically induced liquefaction and lateral spreading. This condition posed
a potential threat to the stability of the proposed wharf structures during and
after major earthquakes. A CDSM buttress system was proposed to provide
shoreline stabilization and control lateral spreading.
The soil-cement buttress consisted of a rectangular grid of
Cement Deep Soil Mixing (CDSM) walls formed using 3-foot diameter columns spaced
on 2-foot centers. In the shallow Bay Mud area, the grid consisted of two
longitudinal walls parallel to the shoreline spaced 31 feet apart, and a series
of transverse walls perpendicular to the shoreline spaced twelve feet apart. In
the deep Bay Mud area, the width of the CDSM grid was increased by extending the
transverse walls in the direction of the shoreline slope. When the width of the
CDSM grid was greater than 68.5 feet, a third longitudinal wall was added. The
maximum treatment depth in the deep Bay Mud area was 88 feet.
Over 60,000 cubic yards of CDSM ground stabilization was
constructed over a period of five months. Triple-shaft CDSM equipment with a
real-time monitoring system was used for ground stabilization.
Test specimens for unconfined compressive strength were retrieved
by a triple barrel coring system, and exceeded the acceptance criteria of an
average of 150 psi at 28 days.
|

Soil Mixing on Berths 57/58 with 55/56 (cranes) in
background

Previous Raito Project (lower right) hosts world’s largest
cranes.

Two Raito Soil-Mixing rigs improving ground for Berths
57/58 |
| |
| Oakland International Airport Roadway Project - Oakland, California,
USA |
The construction of the Oakland International Airport Roadway Project for the
airport expansion required the stabilization of subsurface soils for the
construction of three grade separation structures - two roadway interchanges and
one intersection of a roadway and taxiway serving the airport.
Loose, sandy fill and soft Bay Mud were improved by Cement Deep
Soil Mixing (CDSM) for the construction of a soil-cement foundation under MSE
(Mechanically Stabilized Earth) walls for a roadway over-crossing, a soil-cement
gravity retaining wall to maintain stability of a roadway under-crossing during
and after a major earthquake, and a soil-cement-bentonite cutoff wall for
groundwater control.
|
 |
A test section was performed prior to full production to verify
that the CDSM equipment, installation procedures, and mix designs would produce
soil-cement and soil-cement-bentonite with sufficient strength, uniformity, and
permeability to meet the design intent. Additional test sections were performed
for the confirmation or modification of the mix design and installation
procedures to cope with the complex subsurface soil conditions resulting from
the historical development of the site. Test section results revealed that the
CDSM cutoff wall, retaining wall, and foundation could be constructed to satisfy
the design criteria and that the supplemental test sections would alleviate the
impact of the varying subsurface soil conditions.
Over 60,000 cubic yards of CDSM ground improvement and over 8,500
cubic yards of CDSM cutoff wall were constructed over a period of eleven months.
xxxx Triple-shaft CDSM equipment was used for ground stabilization and cutoff
wall installation to a maximum depth of 43 feet. Drilling depth, penetration/
withdrawal speed, shaft rotation and slurry injection rates were monitored on a
real-time basis for accurate mixing control and a uniform mixed product.
Core samples were retrieved from the hardened soil-cement foundation and gravity
retaining walls for strength testing. Test specimens from the
soil-cement-bentonite cutoff wall for strength and permeability testing were
retrieved by wet sampling. Acceptance criteria for unconfined compressive
strength required an average of 150 psi at 28 days for ground stabilization and
an average of 80 psi at 28 days for the cutoff wall. Hydraulic conductivity of
the cutoff wall required a maximum coefficient of 1x10-6 cm/sec.
|
| |
| Caribbean Industrial Facility - Caribbean
Islands |
The CDSM (Cement Deep Soil Mixing) method was used to
construct a grid pattern of soil-cement columns under two
820-foot by 490-foot critical industrial facilities.
The grids were created to prevent the generation of
excessive pore water during and after earthquakes and to
prevent the liquefaction of soils within the foundation
area.
|
 |
| |
| China Harbor - Ensenada, Mexico |
Raito was contracted to build a Cut Off Wall for the city of Ensenada, Mexico.
|
 |
|
Related News: |
|
The world's largest breakwater
has been completed in Mexico. Raito, Inc. helped build the foundation for this 680m
breakwater for the Ensenada, Mexico project.
|
 |
|
|
| |
 |
|
|
|
©2009 Raito, Inc.
|
|
|
|